節后(hou)開工以來,各(ge)地各(ge)行業(ye)鉚足(zu)干(gan)勁,沖刺(ci)一(yi)季度。在集團(tuan)公司承建的連山至賀州公路(廣西段)融資(zi)+工(gong)(gong)(gong)程(cheng)總承包№4標(biao)段(簡(jian)稱“連賀(he)4標(biao)”)一個(ge)個(ge)奮戰場景里,青年員工(gong)(gong)(gong)立足崗位、自我加(jia)壓,秉持著開工(gong)(gong)(gong)即是“決戰”的信念(nian),全力推進項(xiang)目建設。
連賀4標青年員工(gong) 覃岑往/攝
連(lian)賀(he)4標(biao)(biao)主線全(quan)長8.7千(qian)米,橋隧比高達53.8%,全(quan)線“千(qian)溝萬壑(he)”的地形,需累計跨越19處山谷、2條河流(liu)、2處國道,施工條件極其復雜。2024年(nian)是連賀4標(biao)(biao)的通(tong)車攻堅(jian)年(nian),為(wei)充分發揮(hui)項目青(qing)(qing)年(nian)生力軍(jun)和(he)突擊隊作用,連賀4標(biao)(biao)成立了橋梁、路基、隧道、協調、安全(quan)5支青(qing)(qing)年(nian)突擊隊,他們在山巔之上建(jian)起“千(qian)里(li)通(tong)途(tu)”。
黃洞(dong)大寧河(he)大橋(qiao)是連賀高速關鍵控制性工程(cheng)之一,可(ke)謂“牽一發而動全身”,大橋施(shi)工進度(du)的快慢直接影響著(zhu)連賀高速(su)能否按(an)時通車。今年(nian)一季(ji)度(du),大橋主墩要(yao)實現全部封頂(ding),時間緊(jin)、任務重。
黃洞大(da)寧河大(da)橋施工(gong)現場 葉杰(jie)/攝
大橋施工(gong)(gong)管(guan)理員韓(han)軍是(shi)位重慶小伙。春節期間萬家團圓時,他和(he)其他黃洞大寧河大橋建(jian)設者們(men)(men)仍在堅守崗位,進行(xing)大橋墩柱澆筑施工(gong)(gong)。春節復工(gong)(gong)復產后(hou),他們(men)(men)又以更緊張、更飽(bao)滿的狀態(tai)和(he)“滿格”干勁全力推進(jin)項目(mu)建(jian)設。
大(da)橋建設工地上,兩(liang)座塔吊起重機高聳入云(yun),不(bu)斷揮動著吊臂(bei)在云(yun)霄中“翩翩起(qi)舞”,混(hun)(hun)凝土罐(guan)車往來不絕,一斗斗混(hun)(hun)凝土通過料斗被吊送至墩柱(zhu)作業平(ping)臺,橋梁青(qing)年(nian)突擊隊(dui)隊(dui)員爬上(shang)70多米高的墩柱(zhu)靠前(qian)指揮(hui),現場督戰,勞務工人(ren)有條不紊地進行混(hun)(hun)凝土澆筑、振搗及養護等工序,到處是一派(pai)熱(re)火朝(chao)天的大干景象。
韓軍正在(zai)測量黃洞大(da)寧河大(da)橋橋墩鋼筋綁扎間距 覃岑往(wang)/攝
橋梁青年突擊隊員正在(zai)進(jin)行T梁鋼筋(jin)保護(hu)層與鋼筋(jin)間距檢測 覃(tan)岑往/攝
出于(yu)建設需要,連賀4標(biao)累計開通19條臨(lin)時便道、3座(zuo)鋼(gang)棧橋,租用(yong)臨(lin)時用(yong)地(di)(di)800多畝。開工以來,項目協調青年突擊隊員(yuan)主動出擊、擔當作(zuo)為(wei),通過走村串戶耐心(xin)講解征拆政策,以及開展修繕村道、扶困(kun)助農等志愿服務“征”得當地(di)(di)群眾的信任。
當(dang)地村委授(shou)予連(lian)賀4標項目部助力鄉(xiang)村振興錦旗 覃(tan)岑(cen)往/攝
黃(huang)洞(dong)大寧河大橋7號(hao)墩(dun)曾因(yin)電力桿線遷改遲緩嚴重影響施工(gong)進度,對此項(xiang)目組織青(qing)年骨(gu)干進行大(da)(da)橋(qiao)(qiao)施工(gong)方案優(you)(you)化(hua)研討和驗證運算,并積極與(yu)上級部(bu)門進行溝(gou)通協(xie)商,最終決定采(cai)用適當增加掛籃節段懸臂澆(jiao)筑長度,縮(suo)減(jian)(jian)節段數量的(de)方式加快施工(gong)進度。“通過施工(gong)方案的(de)優(you)(you)化(hua),黃洞大(da)(da)寧(ning)河(he)大(da)(da)橋(qiao)(qiao)7號(hao)墩(dun)預計可縮(suo)減(jian)(jian)工(gong)期(qi)20天(tian),我們(men)有信心在一季度實現大(da)(da)橋(qiao)(qiao)主墩(dun)全部(bu)封頂目標(biao),啃(ken)下(xia)‘硬骨(gu)頭’,取得一季度‘開門紅’。”黃洞大(da)(da)寧(ning)河(he)大(da)(da)橋(qiao)(qiao)工(gong)區(qu)長、橋(qiao)(qiao)梁突擊隊隊員潘(pan)曉(xiao)斗志滿滿。
黃洞(dong)大寧河大橋7號(hao)墩(dun)右幅(fu)墩(dun)身澆(jiao)筑(zhu) 覃岑往/攝
越是(shi)項目(mu)趕工關鍵時刻,越是(shi)不能(neng)急于求成。為保(bao)障項目(mu)建(jian)設安全優質高效推進,連(lian)賀4標青年員工(gong)立足各自崗位、通(tong)力協作,為項目建(jian)設獻智獻策(ce)。
連(lian)賀4標二工(gong)(gong)區(qu)路基(ji)施工(gong)(gong) 覃岑往/攝
連賀4標技術員(yuan)對(dui)(dui)全(quan)線工(gong)(gong)程進(jin)度進(jin)行(xing)(xing)詳(xiang)細(xi)整理(li)(li)(li)匯總(zong),認真倒排工(gong)(gong)期,明確節點目(mu)標,將施(shi)工(gong)(gong)目(mu)標數據(ju)(ju)化(hua)、可視化(hua);現(xian)場(chang)管(guan)(guan)理(li)(li)(li)人員(yuan)在(zai)做好各工(gong)(gong)區施(shi)工(gong)(gong)管(guan)(guan)理(li)(li)(li)的(de)同時,加(jia)強(qiang)對(dui)(dui)勞務(wu)工(gong)(gong)人的(de)教育(yu)培訓和(he)(he)班(ban)前交底,提(ti)高勞務(wu)工(gong)(gong)人的(de)技術水平;材料(liao)物資(zi)管(guan)(guan)理(li)(li)(li)人員(yuan)在(zai)做好材料(liao)采購儲備的(de)同時,根(gen)據(ju)(ju)現(xian)場(chang)實(shi)際情況,對(dui)(dui)全(quan)線進(jin)行(xing)(xing)“量體裁衣”般科學統(tong)籌調配,保(bao)證現(xian)場(chang)施(shi)工(gong)(gong)高效(xiao)運轉;機械設備管(guan)(guan)理(li)(li)(li)人員(yuan)加(jia)強(qiang)對(dui)(dui)機械設備的(de)檢修,對(dui)(dui)新進(jin)場(chang)設備進(jin)行(xing)(xing)嚴格審查(cha)檢驗,確保(bao)每一(yi)臺機械設備都能(neng)(neng)發揮最(zui)佳效(xiao)能(neng)(neng);安全(quan)生產(chan)管(guan)(guan)理(li)(li)(li)人員(yuan)加(jia)強(qiang)對(dui)(dui)隧道、高邊坡和(he)(he)橋梁(liang)墩柱等重大風(feng)險源的(de)安全(quan)巡查(cha)力(li)度,及時發現(xian)并消(xiao)除現(xian)場(chang)施(shi)工(gong)(gong)安全(quan)隱患,為項目(mu)建設保(bao)駕(jia)護(hu)航。
青(qing)年員工在掛圖作戰室復(fu)盤磨刀大橋當(dang)日產(chan)值完成情(qing)況 覃岑往/攝
此外,項目(mu)成立了(le)掛圖作(zuo)戰室,每日(ri)施工(gong)結(jie)束后,各青年突(tu)擊隊員(yuan)都會集中(zhong)到掛圖作(zuo)戰室,對每日(ri)產值完成情況進行詳細標注,互相(xiang)比(bi)拼,探討總結(jie)施工(gong)經驗,對不(bu)足之處進行及時糾偏(pian),形成“比學趕幫超”的(de)良好氛圍(wei),全面掀起項目(mu)大干熱潮。
節(jie)后(hou)全(quan)面復工以來(lai),連(lian)賀4標2個混(hun)凝土拌合站“滿血”運營,200多(duo)(duo)臺施(shi)工機(ji)械開足馬力(li),1000多(duo)(duo)名工人(ren)各司其職,項(xiang)目工程(cheng)進度不斷刷新,施(shi)工現場一天一個樣(yang)。截至(zhi)目前,連賀4標路基軟基換填全部完(wan)成,挖(wa)方(fang)、填方(fang)完(wan)成率超過(guo)80%;橋(qiao)梁樁基完(wan)成率超80%,黃洞(dong)大寧河大橋(qiao)6號墩順利封(feng)頂(ding);隧道工程(cheng)累計進尺突(tu)破2000米。